Project Profile | Industrial, Medium/High Voltage

Terminal 46 Substation 1 Replacement

LOCATION:

Seattle, WA

CONTRACT VALUE:

$6 Million

This design-build project upgraded critical infrastructure that was previously deemed unsafe and did not meet NEC standards. EC was an instrumental contributor to the design and construction of new Seattle City Light (SCL) infrastructure, including a four-way pad-mounted switchgear, a 2,000 kVA transformer, and a new primary substation building, all built to the Port of Seattle and SCL standards.